Maintenance of New Facilities (2025-26)

The CSU is scheduled to open 296,528 square feet of new facilities in 2025-26. The cost to fund regular maintenance of these facilities is $23.6 per square foot, for a total of $7 million in 2025-26. Regular maintenance of new facilities includes the cost of utilities, building maintenance, custodial, landscape and administrative support.

CampusFacility #Facility NameCompletion Date (M-Y)2025/26 New Space - Square FootageAmount at $23.60/ft²
Dominguez Hil​​ls106AOrthotics & Prosthetics SciencesNov-255,000$118,000
Fresno015Engineering EastNov-242,265$53,000
Fullerton008GVisual Arts - Unit GJul-2415,288$361,000
008HVisual Arts - Unit HJul-2437,027$874,000
Subtotal52,315$1,235,000
Humboldt177StewartSep-2422,572$533,000
114Engineering & TechnologyMay-2672,783$1,718,000
Subtotal95,355$2,251,000
San Diego (Calexico)102Brawley Science & EngineeringJul-2540,789$963,000
San Luis Obispo065University UnionSep-2314,084$332,000
113Sierra Madre HallSep-233,198$75,000
010TLibrary SurgeSep-234,851$115,000
042ETennis ClubhouseJul-24358$8,000
074John Madden Football CenterSep-234,253$100,000
159Plant Sciences ComplexNov-2521,800$515,000
165Animal Health CenterNov-2520,440$482,000
Subtotal68,984$1,627,000
San Marcos038FUniversity Village DiningJun-262,512$59,000
Stanislaus (Stockton)002Acacia Replacement BuildingJun-2511,940$282,000
Total279,160$6,588,000