Maintenance of New Facilities (2024-25)

The CSU is scheduled to open 532,130 square feet of new facilities in 2024-25. The cost to fund regular maintenance of these facilities is $23.79 per square foot, for a total of $12.5 million in 2024-25. Regular maintenance of new facilities includes the cost of utilities, building maintenance, custodial, landscape and administrative support.

CampusFacility #Facility NameCompletion Date (M-Y)Square FootageAmount at $23.79/sqft
Bakersfield024LorienJan-2310,437$248,000
025EntwoodJan-2310,437$248,000
026DobryJan-2310,437$248,000
027RivendellJan-2310,437$248,000
028NumenorJan-2310,437$248,000
029RohanJan-2310,437$248,000
Subtotal62,622$1,488,000
Chico102Butte Hall Replacement BuildingMay-2498,000$2,331,000
088University Services BuildingNov-2422,320$531,000
390FARM Agricultural Learning & Training CenterMay-2510,000$127,000
Subtotal130,320$2,989,000
Dominguez Hills131Women’s Resource CenterAug-231,420$34,000
East Bay071Applied Science CenterSep-2422,165$527,000
Fresno​
133LModular 133LFeb-23514$12,000
133MModular 133MFeb-23433$10,000
133NModular 133NFeb-23188$5,000
133PModular 133PFeb-23157$4,000
133QModular 133QFeb-232,880$69,000
133RModular 133R
Feb-23985$23,000
133SModular 133SFeb-23985$23,000
Subtotal6,142$146,000
Long Beach05AFamily and Consumer SciencesNov-246,200$148,000
081Neil & Phyllis Barrett Athletic Admin CenterSep-2410,289$245,000
Subtotal16,489$393,000
Monterey Bay036University StorageJun-221,920$46,000
703UPD AnnexJan-224,308$103,000
Subtotal6,228$149,000
Northridge014Autodesk Technology Engagement CenterDec-2434,000$809,000
Pomona028APlant Sciences Laboratory (Temp. Modular)Jan-24960$23,000
Sacramento2506011 FolsomDec-1813,588$323,000
San Bernardino020APerforming Arts CenterNov-2473,337$1,745,000
San Diego314New Substation AAug-232,442$58,000
San Francisco104AWest Campus Green Student Health and Dining CenterJan-2538,433$914,000
049RTC 49Jun-2219,659$468,000
Subtotal58,092$1,382,000
San Luis Obispo480Cal Poly Administrative Services CenterJan-2446,386$1,104,000
Stanislaus014Child Development CenterJul-238,880$211,000
002Acacia Replacement Building, Phase 1Jun-2543,230$1,028,000
024Magnolia MansionAug-255,829$139,000
Subtotal57,939$1,378,000
Total532,130$12,548,000