Maintenance of New Facilities

The CSU is scheduled to open 363,486 square feet of new facilities in 2026-27. The cost to fund regular maintenance of these facilities is $24.72 per square foot, for a total of $9 million in 2026-27. Regular maintenance of new facilities includes the cost of utilities, building maintenance, custodial, landscape and administrative support. An additional $10.75 per square foot (3.9 million) will support systemwide deferred maintenance needs, resulting in a combined total of $12.9 million.


Campus Facility # Facility Name​​
Completion
Date (M-Y)
2026-27 New Space-Square FootageAmount at $24.72/ft1
Bakersfield
078
Food Pantry
Mar-26
2,400
$59,000
Channel Islands
009 Gateway Hall Aug-25 42,803 $1,058,000
037 Shasta Hall
Sep-25 19,181 $474,000
041 Marin Hall Aug-25 27,636 $683,000
89,620 $2,215,000
Chico 105 Human ID Lab Jun-27 28,600 $707,000
209 388 Orange Street Jul-25 5,783 $143,000
34,383 $850,000
Dominguez Hills 074 Dining Commons May-26 4,176 $103,000
156 Health & Wellness Recreation Center Oct-26 8,175 $202,000
12,351 $305,000
Fresno 099B Corp Yard Boiler Plant Jun-27 434 $11,000
229 Meats Lab Jun-27 6,880 $170,000

7,314 $181,000
Fullerton 084 ECS Innovation Hub Apr-27 45,998 $1,137,000
Humboldt 007 Jenkins Hall Aug-25 3,926 $97,000
Monterey Bay 052 Taylor Science and Engineering Building Jun-27 17,584 $435,000
Northridge 130 Matador Success and Inclusion Center Jun-27 49,669 $1,228,000
San Diego 119 Duran Sciences (formerly Life Sciences) Jun-27 79,700 $1,970,000
907 6475 Alvarado Rd. Jan-25 2,216 $55,000
81,916 $2,025,000
San Luis Obispo 015 Corporation Administration Jun-25 13,260 $328,000
181 William and Linda Frost Center–Addition Jul-26 800 $20,000
079 Water Reclamation Facility Aug-26 2,658 $66,000
004 Research Development Center Jan-26 1,607 $40,000
18,325 $453,000
Total 363,486 $8,985,000

Systemwide Deferred Maintenance
$3,908,000
​​
​​Grand Total
$12,893,000


​​