Maintenance of New Facilities

Each year, the CSU opens new facilities across the 23 campuses. For 2021-22, the CSU is opening 559,000 square feet of new facilities, as shown in the table below. At a per square foot rate of $20.28 for 2021-22, the CSU is requesting over $11.3 million to fully fund the maintenance requirements of these new facilities. Regular maintenance of new facilities includes the cost of utilities, building maintenance, custodial, landscape, and administrative support. This funding will sustain budgets needed to open and operate new buildings.

​The maintenance of new facilities is budgeted at $20.28 per square foot which is calculated based on actual expenditures on maintenance and repair of buildings as they age. Campuses use productivity and efficiency management strategies to satisfy a portion of this unfunded need, but they often have to delay repairs.

Campus Facility # Facilit​​y Name
Completion
Date (M-Y)
Square Footage ​Amount at $20.28/sqft
​Channel Islands027
Manzanita Hall
Jul-20
6,761
$137,000
Dominguez Hills
157
Innovation and Instruction
Mar-21
108,721
$2,205,000
East Bay
070
CORE Building
Mar-22
100,000 ​$2,028,000
Fullerton
101A
Modular Trailer
Jun-20
1,83837,000

​101B
Modular Trailer​
Jun-20​​1,838
37,000​

102A​Modular Trailer​Jun-20​​890
18,000​

102B​Modular Trailer​Jun-20​890​18,000​

102C​Modular Trailer​Jun-20​890​18,000​

102D​Modular Trailer​Jun-20​1,310​27,000​

102E​Modular Trailer​Jun-20​1,310​27,000​

102F​Modular Trailer​Jun-20​1,310​27,000​

102G​Modular Trailer​Jun-20​1,310​27,000​

102H​​Modular Trailer
​Jun-20
​425
9,000​

102GI
Modular Trailer​Jun-20​155​3,000​


12,166​ $248,000
​Humboldt
​041
​Library
​Aug-20
5,312
​$108,000
​Long Beach
​084
Horn Center​​Aug-21
4,300
​$87,000
​Maritime
​069
​Classroom Anne​x
​Dec-20
​4,160
​84,000

100​
​Vallejo
​Aug-20
​11,844
​$240,000




16,004​ $324,000
Monterey Bay
504
Academic III
Jun-19
4,000 $81,000
San José

112
Interdisciplinary Science
Dec-21
164,715
$3,340,000
San Luis Obispo
181
Science and Agriculture Teaching and Research Complex
Aug-21
105,091
$2,131,000

Sonoma
001​
Stevenson Hall
May-22
31.899
$647,000
​​​​​Total Amount for New Facilities


558,969 ​​$11,336,000