| AD NOAT 07-040 | ||||||||
| ATTACHMENT B | ||||||||
| Adjustments to 2006/07 1st Quarter State Fire Marshal (reflected in the total due SFM): | ||||||||
| 2005/06 4th quarter SFM - AD NOAT 06-230 | ||||||||
| Campus | Hours | Rate | Credit | Debit | Comment | |||
| Maritime Academy | 50.00 | 140.00 | $ - | $7,000.00 | Disputed services not enough info.-Annual Inspection per SFM | |||
| San Luis Obispo | 1.00 | 140.00 | $ 140.00 | $ - | Construction services; to be paid by CPDC | |||
| CPDC | 1.00 | 140.00 | $ - | $ 140.00 | Construction services; previously paid by SLO | |||
| $ 140.00 | $7,140.00 | |||||||
| If you have any questions, please contact Nancy Freelander-Paice at (562) 951-4087 | ||||||||
| or email nfreelander-paice@calstate.edu | ||||||||