Deferred Maintenance

Deferred Maintenance occurs when scheduled repairs are delayed to subsequent years due to project cost, timing, and/or lack of available resources. Historically the CSU has also used the term Deferred Maintenance to include the delayed replacement of building systems that have exceeded their useful life. This chart shows the growth of the Deferred Maintenance backlog since 1993/94 along with the funding provided to address this backlog.

CSU Deferred Maintenance Backlog Projections from 1993/94 to 2014/15
Budget Year CA-CPI
% Change
Budget
Funding
Offset
(in millions)
Backlog
(in millions)
1993/94 Base     $351.0
1994/95 1.8% $17.0 340.3
1995/96 1.7% 24.0 322.1
1996/97 1.4% - 326.6
1997/98 2.3% - 334.1
1998/99 2.0% 20.0 320.8
1999/00 2.5% - 328.8
2000/01 3.2% 2.8 336.5
2001/02 4.3% - 351.0
2002/03 2.9% - 361.2
2003/04 2.6% - 370.6
2004/05 1.9% - 377.6
2005/06 3.3% 1.5 388.6
2006/07 4.2% 2.5 402.4
2007/08 3.4% 2.5 413.6
2008/09 3.4% - 427.6
2009/10 1.3% - 433.2
2010/11 0.7% - 436.2
2011/12 1.7% - 443.7
2012/13 2.4% - 454.3
2013/14 2.1% - 463.8
2014/15 2.0% - $473.1

CA-CPI % Source: CA Department of Finance, Planning Estimate Forecast, July
(calculated using a formula developed by the CA Dept. of Industrial Relations)